Briefing/projectactive
Coyote Ridge BESS is a 111 MW Battery project in Texas, currently active.
Grenergy USA is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-10-06.
- Queue ID
- ERCOT-27INR0432
- Location
- Brown, Texas
- Technology
- Battery
- Developer
- Grenergy USA
- Market / region
- ERCOT
- Point of interconnection
- 292 Holder 138 kV
What stands out
1
Coyote Ridge BESS is a 111 MW Battery project in Texas with status active.
2
Grenergy USA is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2027-10-06.
Market and operating context
- Queue date
- 2025-01-28
- Proposed COD
- 2027-10-06
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.