Query
Cove Mountain Solar
Type
Entity Briefing
Entity
Black Mountain Hale Gas
State
MT
Technology
solar
Generated
2026-10-05T03:50:42.896Z

Briefing on Black Mountain Hale Gas

Entity Briefing
Generated Oct 5, 2026·Dataset freshness not reported
991 MW
Proposed capacity
active
Current status
Gas
Technology
ERCOT
Market / region
2029-09-28
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Black Mountain Hale Gas is a 991 MW Gas project in Texas, currently active.

Fort Worth Power Core LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-09-28.

Queue ID
ERCOT-29INR0175
Location
Hale, Texas
Technology
Gas
Developer
Fort Worth Power Core LLC
Market / region
ERCOT
Point of interconnection
345 kV Blackwater Draw Switch (#23920)

What stands out

1

Black Mountain Hale Gas is a 991 MW Gas project in Texas with status active.

2

Fort Worth Power Core LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2029-09-28.

Market and operating context

Queue date
2025-08-27
Proposed COD
2029-09-28
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Black Mountain Hale Gas — verified asset snapshot

FieldValue
Queue IDERCOT-29INR0175
LocationHale, Texas
TechnologyGas
DeveloperFort Worth Power Core LLC
Market / regionERCOT
Point of interconnection345 kV Blackwater Draw Switch (#23920)
Queue date2025-08-27
Proposed COD2029-09-28