Entity
Coastal Bayou Storage
Generated
2026-10-19T13:59:28.055Z

Briefing on Coastal Bayou Storage

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
175 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2027-06-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Coastal Bayou Storage is a 175 MW Battery project in Texas, currently active.

TOCE TX BESS 5, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-06-01.

Queue ID
ERCOT-26INR0552
Location
Harris, Texas
Technology
Battery
Developer
TOCE TX BESS 5, LLC
Market / region
ERCOT
Point of interconnection
Tap 138kV #40015 Cedar Bayou Plant - #40050 Sjolander Ckt 86

What stands out

1

Coastal Bayou Storage is a 175 MW Battery project in Texas with status active.

2

TOCE TX BESS 5, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-06-01.

Market and operating context

Queue date
2024-09-04
Proposed COD
2027-06-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Coastal Bayou Storage — verified asset snapshot

FieldValue
Queue IDERCOT-26INR0552
LocationHarris, Texas
TechnologyBattery
DeveloperTOCE TX BESS 5, LLC
Market / regionERCOT
Point of interconnectionTap 138kV #40015 Cedar Bayou Plant - #40050 Sjolander Ckt 86
Queue date2024-09-04
Proposed COD2027-06-01