Query
Clutch City Solar Phase II
Type
Entity Briefing
Entity
Clutch City Solar Phase II
Generated
2026-10-19T09:51:41.418Z

Briefing on Clutch City Solar Phase II

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
251 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2028-07-01
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Clutch City Solar Phase II is a 251 MW Solar project in Texas, currently active.

HZ SOLAR I, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2028-07-01.

Queue ID
ERCOT-25INR0330
Location
Brazoria, Texas
Technology
Solar
Developer
HZ SOLAR I, LLC
Market / region
ERCOT
Point of interconnection
tap 138kV 42960 Mustang Bayou – 42100 Hudson CKT#04

What stands out

1

Clutch City Solar Phase II is a 251 MW Solar project in Texas with status active.

2

HZ SOLAR I, LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2028-07-01.

Market and operating context

Queue date
2023-02-20
Proposed COD
2028-07-01
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Clutch City Solar Phase II — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0330
LocationBrazoria, Texas
TechnologySolar
DeveloperHZ SOLAR I, LLC
Market / regionERCOT
Point of interconnectiontap 138kV 42960 Mustang Bayou – 42100 Hudson CKT#04
Queue date2023-02-20
Proposed COD2028-07-01