Briefing/projectactive
Chesterfield CT Units 1 and 2 is a 569 MW Gas project in Virginia, currently active.
Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) is the reported developer. The reported queue phase is TC1. Proposed COD is 2029-12-31.
- Queue ID
- PJM-AF1-128
- Location
- Chesterfield, Virginia
- Technology
- Gas
- Developer
- Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
- Market / region
- PJM
- Point of interconnection
- Chesterfield 230 kV
What stands out
1
Chesterfield CT Units 1 and 2 is a 569 MW Gas project in Virginia with status active.
2
Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) is the reported developer.
3
The reported queue phase is TC1; proposed COD is 2029-12-31.
Market and operating context
- Queue date
- 2019-09-18
- Proposed COD
- 2029-12-31
- IA status
- IA Pending
- Study phase
- TC1
- Service type
- NRIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.