Briefing/projectsuspended
Chester Solar is a 120 MW Solar project in Virginia, currently suspended.
The reported queue phase is IA Executed. Proposed COD is 2027-10-29.
- Queue ID
- PJM-AE2-027
- Location
- Chesterfield, Virginia
- Technology
- Solar
- Market / region
- PJM
- Point of interconnection
- Harrowgate-Locks 115kV
What stands out
1
Chester Solar is a 120 MW Solar project in Virginia with status suspended.
2
The reported queue phase is IA Executed; proposed COD is 2027-10-29.
3
Latest linked story: “Updated: $2B solar farm-data center hybrid pitched for Chesterfield ‘megasite’” (Richmond BizSense, 2019-05-28).
Market and operating context
- Queue date
- 2018-12-20
- Proposed COD
- 2027-10-29
- IA status
- IA Executed
- Study phase
- IA Executed
- Service type
- NRIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.