Query
Chester Solar
Type
Entity Briefing
Entity
Chester Solar
Generated
2026-10-06T14:28:18.041Z

Briefing on Chester Solar

Entity Briefing
Generated Oct 6, 2026·Dataset freshness not reported
120 MW
Proposed capacity
suspended
Current status
Solar
Technology
PJM
Market / region
2027-10-29
Proposed COD
IA Executed
Queue phase
Briefing/projectsuspended

Chester Solar is a 120 MW Solar project in Virginia, currently suspended.

The reported queue phase is IA Executed. Proposed COD is 2027-10-29.

Queue ID
PJM-AE2-027
Location
Chesterfield, Virginia
Technology
Solar
Market / region
PJM
Point of interconnection
Harrowgate-Locks 115kV

What stands out

1

Chester Solar is a 120 MW Solar project in Virginia with status suspended.

2

The reported queue phase is IA Executed; proposed COD is 2027-10-29.

3

Latest linked story: “Updated: $2B solar farm-data center hybrid pitched for Chesterfield ‘megasite’” (Richmond BizSense, 2019-05-28).

Market and operating context

Queue date
2018-12-20
Proposed COD
2027-10-29
IA status
IA Executed
Study phase
IA Executed
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Chester Solar — verified asset snapshot

FieldValue
Queue IDPJM-AE2-027
LocationChesterfield, Virginia
TechnologySolar
Market / regionPJM
Point of interconnectionHarrowgate-Locks 115kV
Queue date2018-12-20
Proposed COD2027-10-29
IA statusIA Executed