Briefing on Champion Road BESS

Entity Briefing
Generated Sep 19, 2026·Dataset freshness not reported
206 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-09-30
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Champion Road BESS is a 206 MW Battery project in Texas, currently active.

Horizon Energy Storage Greenfield Project Holdings LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-09-30.

Queue ID
ERCOT-28INR0300
Location
Angelina, Texas
Technology
Battery
Developer
Horizon Energy Storage Greenfield Project Holdings LLC
Market / region
ERCOT
Point of interconnection
138 kV Tap 3328 Lufkin South - 3324 Lufkin Switch Tap East

What stands out

1

Champion Road BESS is a 206 MW Battery project in Texas with status active.

2

Horizon Energy Storage Greenfield Project Holdings LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-09-30.

Market and operating context

Queue date
2025-02-14
Proposed COD
2028-09-30
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Champion Road BESS — verified asset snapshot

FieldValue
Queue IDERCOT-28INR0300
LocationAngelina, Texas
TechnologyBattery
DeveloperHorizon Energy Storage Greenfield Project Holdings LLC
Market / regionERCOT
Point of interconnection138 kV Tap 3328 Lufkin South - 3324 Lufkin Switch Tap East
Queue date2025-02-14
Proposed COD2028-09-30