Briefing on CG Fulton County

Entity Briefing
Generated Oct 10, 2026·Dataset freshness not reported
199 MW
Proposed capacity
active
Current status
Solar
Technology
PJM
Market / region
2028-05-31
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

CG Fulton County is a 199 MW Solar project in Ohio, currently active.

The reported queue phase is IA Executed. Proposed COD is 2028-05-31.

Queue ID
PJM-AF1-206
Location
Fulton, Ohio
Technology
Solar
Market / region
PJM
Point of interconnection
East Fayette 138 kV

What stands out

1

CG Fulton County is a 199 MW Solar project in Ohio with status active.

2

The reported queue phase is IA Executed; proposed COD is 2028-05-31.

3

Latest linked story: “Ohio approves 199-MW solar project in Fulton County” (wtol.com, 2025-11-20).

Market and operating context

Queue date
2019-09-26
Proposed COD
2028-05-31
IA status
IA Executed
Study phase
IA Executed
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

CG Fulton County — verified asset snapshot

FieldValue
Queue IDPJM-AF1-206
LocationFulton, Ohio
TechnologySolar
Market / regionPJM
Point of interconnectionEast Fayette 138 kV
Queue date2019-09-26
Proposed COD2028-05-31
IA statusIA Executed