Briefing/projectactive
Ceres BESS is a 203 MW Battery project in Texas, currently active.
Ceres BESS, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-11-30.
- Queue ID
- ERCOT-26INR0464
- Location
- Hunt, Texas
- Technology
- Battery
- Developer
- Ceres BESS, LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 138 kV 6883 QUINLAN NORTH SS - 6860 UNION VALLEY SS
What stands out
1
Ceres BESS is a 203 MW Battery project in Texas with status active.
2
Ceres BESS, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2027-11-30.
Market and operating context
- Queue date
- 2024-10-29
- Proposed COD
- 2027-11-30
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.