Briefing/projectactive
Centennial Solar is a 61 MW Solar project in Texas, currently active.
Centennial AD 8 LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-04-30.
- Queue ID
- ERCOT-26INR0372
- Location
- Menard, Texas
- Technology
- Solar
- Developer
- Centennial AD 8 LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 138kV 6364 YELLOW JACKET - 76390 FORT MASON
What stands out
1
Centennial Solar is a 61 MW Solar project in Texas with status active.
2
Centennial AD 8 LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2029-04-30.
4
Latest linked story: “Woolly ‘Lambscapers’ Back at Alamo 2 Solar Farm” (San Antonio Report, 2015-05-13).
Market and operating context
- Queue date
- 2024-01-03
- Proposed COD
- 2029-04-30
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.