16 MW
Proposed capacity
suspended
Current status
Solar
Technology
PJM
Market / region
2027-12-31
Proposed COD
IA Executed
Queue phase
Briefing/projectsuspended

CE-FILMORE is a 16 MW Solar project in Pennsylvania, currently suspended.

The reported queue phase is IA Executed. Proposed COD is 2027-12-31.

Queue ID
PJM-AE2-248
Location
Centre, Pennsylvania
Technology
Solar
Market / region
PJM
Point of interconnection
Fillmore-Thompson Farm 46 kV

What stands out

1

CE-FILMORE is a 16 MW Solar project in Pennsylvania with status suspended.

2

The reported queue phase is IA Executed; proposed COD is 2027-12-31.

Market and operating context

Queue date
2019-03-25
Proposed COD
2027-12-31
IA status
IA Executed
Study phase
IA Executed
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

CE-FILMORE — verified asset snapshot

FieldValue
Queue IDPJM-AE2-248
LocationCentre, Pennsylvania
TechnologySolar
Market / regionPJM
Point of interconnectionFillmore-Thompson Farm 46 kV
Queue date2019-03-25
Proposed COD2027-12-31
IA statusIA Executed