Cartersville Solar is a 100 MW Solar project in Virginia, currently suspended.
The reported queue phase is IA Executed. Proposed COD is 2026-05-17.
- Queue ID
- PJM-AC2-165
- Location
- Powhatan, Virginia
- Technology
- Solar
- Market / region
- PJM
- Point of interconnection
- Bremo-Powhatan 230kV
What stands out
1
Cartersville Solar is a 100 MW Solar project in Virginia with status suspended.
2
The reported queue phase is IA Executed; proposed COD is 2026-05-17.
3
Latest linked story: “New solar panel farm installed in Powhatan County” (WRIC ABC 8News, 2025-03-05).
Market and operating context
- Queue date
- 2017-03-30
- Proposed COD
- 2026-05-17
- IA status
- IA Executed
- Study phase
- IA Executed
- Service type
- NRIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.