Briefing on Caracara Energy Storage Center

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
203 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-08-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Caracara Energy Storage Center is a 203 MW Battery project in Texas, currently active.

FRESH AIR ENERGY II, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-08-01.

Queue ID
ERCOT-28INR0020
Location
Bexar, Texas
Technology
Battery
Developer
FRESH AIR ENERGY II, LLC
Market / region
ERCOT
Point of interconnection
Tap 138kV 5055 Cagnon - 5346 Potranco

What stands out

1

Caracara Energy Storage Center is a 203 MW Battery project in Texas with status active.

2

FRESH AIR ENERGY II, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-08-01.

Market and operating context

Queue date
2024-05-09
Proposed COD
2028-08-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Caracara Energy Storage Center — verified asset snapshot

FieldValue
Queue IDERCOT-28INR0020
LocationBexar, Texas
TechnologyBattery
DeveloperFRESH AIR ENERGY II, LLC
Market / regionERCOT
Point of interconnectionTap 138kV 5055 Cagnon - 5346 Potranco
Queue date2024-05-09
Proposed COD2028-08-01