Caney Creek Solar is a 121 MW Solar project in Texas, currently active.
HEP Aquamarine Holdings LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-06-21.
- Queue ID
- ERCOT-23INR0045
- Location
- Van Zandt, Texas
- Technology
- Solar
- Developer
- HEP Aquamarine Holdings LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 138kV 6829 Glen Pine - 6833 Explorer
What stands out
Caney Creek Solar is a 121 MW Solar project in Texas with status active.
HEP Aquamarine Holdings LLC is the reported developer.
The reported queue phase is IA Executed; proposed COD is 2027-06-21.
Latest linked story: “Insights from the Odessa II Power System Disturbance” (TRC Companies, 2023-02-23).
Market and operating context
- Queue date
- 2020-09-25
- Proposed COD
- 2027-06-21
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.