Briefing on Camellia Storage

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
91 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-06-30
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Camellia Storage is a 91 MW Battery project in Texas, currently active.

Camellia Storage Project LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-06-30.

Queue ID
ERCOT-23INR0480
Location
Hidalgo, Texas
Technology
Battery
Developer
Camellia Storage Project LLC
Market / region
ERCOT
Point of interconnection
Tap 138 kV 8358 NORTH MERCEDES - 8327 HARLINGEN 138 kV

What stands out

1

Camellia Storage is a 91 MW Battery project in Texas with status active.

2

Camellia Storage Project LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-06-30.

Market and operating context

Queue date
2022-07-05
Proposed COD
2028-06-30
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Camellia Storage — verified asset snapshot

FieldValue
Queue IDERCOT-23INR0480
LocationHidalgo, Texas
TechnologyBattery
DeveloperCamellia Storage Project LLC
Market / regionERCOT
Point of interconnectionTap 138 kV 8358 NORTH MERCEDES - 8327 HARLINGEN 138 kV
Queue date2022-07-05
Proposed COD2028-06-30