Briefing/projectactive
Cachena Solar SLF is a 601 MW Solar+Battery project in Texas, currently active.
Clear Fork Creek Solar LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-04-29.
- Queue ID
- ERCOT-23INR0027
- Location
- Wilson, Texas
- Technology
- Solar+Battery
- Developer
- Clear Fork Creek Solar LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345KV 5133 Elm Creek - 5323 Old Hickory
What stands out
1
Cachena Solar SLF is a 601 MW Solar+Battery project in Texas with status active.
2
Clear Fork Creek Solar LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2027-04-29.
Market and operating context
- Queue date
- 2020-05-01
- Proposed COD
- 2027-04-29
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.