Briefing/projectactive
Buzzi Maryneal Wind Project is a 18 MW Wind project in Texas, currently active.
Buzzi Unicem USA is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2026-01-02.
- Queue ID
- ERCOT-26INR0297
- Location
- Nolan, Texas
- Technology
- Wind
- Developer
- Buzzi Unicem USA
- Market / region
- ERCOT
- Point of interconnection
- 1413 SWEETCRK-9
What stands out
1
Buzzi Maryneal Wind Project is a 18 MW Wind project in Texas with status active.
2
Buzzi Unicem USA is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2026-01-02.
Market and operating context
- Queue date
- 2023-10-25
- Proposed COD
- 2026-01-02
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.