Query
Buttercup Wind
Type
Entity Briefing
Entity
Buttercup Wind
Technology
wind
Generated
2026-10-11T01:04:36.484Z

Briefing on Buttercup Wind

Entity Briefing
Generated Oct 11, 2026·Dataset freshness not reported
50 MW
Proposed capacity
active
Current status
Wind
Technology
NYISO
Market / region
2029-12-01
Proposed COD
C24
Queue phase
Briefing/projectactive

Buttercup Wind is a 50 MW Wind project in New York, currently active.

Buttercup Wind LLC is the reported developer. The reported queue phase is C24. Proposed COD is 2029-12-01.

Queue ID
NYISO-C24-229
Location
Chautauqua, New York
Technology
Wind
Developer
Buttercup Wind LLC
Market / region
NYISO
Point of interconnection
Dunkirk-Falconer Line 160 115kV

What stands out

1

Buttercup Wind is a 50 MW Wind project in New York with status active.

2

Buttercup Wind LLC is the reported developer.

3

The reported queue phase is C24; proposed COD is 2029-12-01.

Market and operating context

Queue date
2024-09-21
Proposed COD
2029-12-01
Study phase
C24

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Buttercup Wind — verified asset snapshot

FieldValue
Queue IDNYISO-C24-229
LocationChautauqua, New York
TechnologyWind
DeveloperButtercup Wind LLC
Market / regionNYISO
Point of interconnectionDunkirk-Falconer Line 160 115kV
Queue date2024-09-21
Proposed COD2029-12-01