Briefing/projectactive
Burro Loco Energy Storage is a 25 MW Battery project in Texas, currently active.
VESI Upton County BESS, is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-09-15.
- Queue ID
- ERCOT-24INR0319
- Location
- Cameron, Texas
- Technology
- Battery
- Developer
- VESI Upton County BESS,
- Market / region
- ERCOT
- Point of interconnection
- 8626 Resaca 69kV
What stands out
1
Burro Loco Energy Storage is a 25 MW Battery project in Texas with status active.
2
VESI Upton County BESS, is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2028-09-15.
Market and operating context
- Queue date
- 2022-07-18
- Proposed COD
- 2028-09-15
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.