Buckaroo BESS is a 120 MW Battery project in Texas, currently active.
Weatherford BESS LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-12-08.
- Queue ID
- ERCOT-26INR0498
- Location
- Parker, Texas
- Technology
- Battery
- Developer
- Weatherford BESS LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 138kV BROCK(487) – STHBROCKSW(489)
What stands out
1
Buckaroo BESS is a 120 MW Battery project in Texas with status active.
2
Weatherford BESS LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2027-12-08.
Market and operating context
- Queue date
- 2024-05-09
- Proposed COD
- 2027-12-08
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.