Briefing on BRP Pictor BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
201 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2025-11-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

BRP Pictor BESS is a 201 MW Battery project in Texas, currently active.

BRP Pictor BESS LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2025-11-01.

Queue ID
ERCOT-22INR0385
Location
Crane, Texas
Technology
Battery
Developer
BRP Pictor BESS LLC
Market / region
ERCOT
Point of interconnection
60400 Lynx 138kV

What stands out

1

BRP Pictor BESS is a 201 MW Battery project in Texas with status active.

2

BRP Pictor BESS LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2025-11-01.

Market and operating context

Queue date
2020-07-24
Proposed COD
2025-11-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

BRP Pictor BESS — verified asset snapshot

FieldValue
Queue IDERCOT-22INR0385
LocationCrane, Texas
TechnologyBattery
DeveloperBRP Pictor BESS LLC
Market / regionERCOT
Point of interconnection60400 Lynx 138kV
Queue date2020-07-24
Proposed COD2025-11-01