Briefing on Brookview Road BESS

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
203 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-05-02
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Brookview Road BESS is a 203 MW Battery project in Texas, currently active.

Brookview Reliability Project LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2028-05-02.

Queue ID
ERCOT-27INR0243
Location
Harris, Texas
Technology
Battery
Developer
Brookview Reliability Project LLC
Market / region
ERCOT
Point of interconnection
Channelview 1 ( 40280) 138kV Substation

What stands out

1

Brookview Road BESS is a 203 MW Battery project in Texas with status active.

2

Brookview Reliability Project LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2028-05-02.

Market and operating context

Queue date
2024-04-09
Proposed COD
2028-05-02
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Brookview Road BESS — verified asset snapshot

FieldValue
Queue IDERCOT-27INR0243
LocationHarris, Texas
TechnologyBattery
DeveloperBrookview Reliability Project LLC
Market / regionERCOT
Point of interconnectionChannelview 1 ( 40280) 138kV Substation
Queue date2024-04-09
Proposed COD2028-05-02