Briefing/projectactive
Brightside Solar Alt POI is a 50 MW Solar project in Texas, currently active.
Brightside Solar, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-08-14.
- Queue ID
- ERCOT-23INR0487
- Location
- Live Oak, Texas
- Technology
- Solar
- Developer
- Brightside Solar, LLC
- Market / region
- ERCOT
- Point of interconnection
- 8156 Charter Substation 138kV
What stands out
1
Brightside Solar Alt POI is a 50 MW Solar project in Texas with status active.
2
Brightside Solar, LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2026-08-14.
Market and operating context
- Queue date
- 2022-05-16
- Proposed COD
- 2026-08-14
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.