Briggs Solar is a 324 MW Solar+Battery project in Texas, currently active.
IP Quantum III, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2028-04-15.
- Queue ID
- ERCOT-23INR0059
- Location
- Haskell, Texas
- Technology
- Solar+Battery
- Developer
- IP Quantum III, LLC
- Market / region
- ERCOT
- Point of interconnection
- tap 345kV 60515 Clear Crossing - 60507 Pendulo
What stands out
1
Briggs Solar is a 324 MW Solar+Battery project in Texas with status active.
2
IP Quantum III, LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2028-04-15.
4
Latest linked story: “Lamar County celebrates commencement of half-billion dollar solar project” (KXII, 2024-11-21).
Market and operating context
- Queue date
- 2020-08-04
- Proposed COD
- 2028-04-15
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.