Briefing/projectactive
Brentwood Energy Storage is a 49 MW Battery project in New York, currently active.
the NY Power Authority is the reported developer. The reported queue phase is C24. Proposed COD is 2028-08-01.
- Queue ID
- NYISO-C24-281
- Location
- Suffolk, New York
- Technology
- Battery
- Developer
- the NY Power Authority
- Market / region
- NYISO
- Point of interconnection
- Brentwood 69 kV Substation
What stands out
1
Brentwood Energy Storage is a 49 MW Battery project in New York with status active.
2
the NY Power Authority is the reported developer.
3
The reported queue phase is C24; proposed COD is 2028-08-01.
Market and operating context
- Queue date
- 2024-09-25
- Proposed COD
- 2028-08-01
- Study phase
- C24
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.