Briefing on Brela BESS LLC

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
251 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-05-29
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Brela BESS LLC is a 251 MW Battery project in Texas, currently active.

Brela BESS LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-05-29.

Queue ID
ERCOT-28INR0030
Location
Wharton, Texas
Technology
Battery
Developer
Brela BESS LLC
Market / region
ERCOT
Point of interconnection
44040 Bailey SW 345 kV

What stands out

1

Brela BESS LLC is a 251 MW Battery project in Texas with status active.

2

Brela BESS LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-05-29.

Market and operating context

Queue date
2024-01-11
Proposed COD
2028-05-29
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Brela BESS LLC — verified asset snapshot

FieldValue
Queue IDERCOT-28INR0030
LocationWharton, Texas
TechnologyBattery
DeveloperBrela BESS LLC
Market / regionERCOT
Point of interconnection44040 Bailey SW 345 kV
Queue date2024-01-11
Proposed COD2028-05-29