Briefing/projectactive
Border Basin is a 120 MW Solar project in Ohio, currently active.
The reported queue phase is IA Executed. Proposed COD is 2026-07-31.
- Queue ID
- PJM-AE1-146
- Location
- Hancock, Ohio
- Technology
- Solar
- Market / region
- PJM
- Point of interconnection
- Ebersole #2-Fostoria Central 138 kV
What stands out
1
Border Basin is a 120 MW Solar project in Ohio with status active.
2
The reported queue phase is IA Executed; proposed COD is 2026-07-31.
3
Latest linked story: “Decision on proposed Arcadia solar farm could fall to county commissioners” (WTOL, 2021-07-29).
Market and operating context
- Queue date
- 2018-09-25
- Proposed COD
- 2026-07-31
- IA status
- IA Executed
- Study phase
- IA Executed
- Service type
- NRIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.