Briefing on Bonita Bateria 2

Entity Briefing
Generated Oct 6, 2026·Dataset freshness not reported
123 MW
Proposed capacity
active
Current status
Battery
Technology
CAISO
Market / region
2029-05-31
Proposed COD
Cluster 15
Queue phase
Briefing/projectactive

Bonita Bateria 2 is a 123 MW Battery project in California, currently active.

The reported queue phase is Cluster 15. Proposed COD is 2029-05-31.

Queue ID
CAISO-2208
Location
Orange, California
Technology
Battery
Market / region
CAISO
Point of interconnection
MARGARITA 138 kV

What stands out

1

Bonita Bateria 2 is a 123 MW Battery project in California with status active.

2

The reported queue phase is Cluster 15; proposed COD is 2029-05-31.

Market and operating context

Queue date
2023-04-17
Proposed COD
2029-05-31
IA status
Not Started
Study phase
Cluster 15
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Bonita Bateria 2 — verified asset snapshot

FieldValue
Queue IDCAISO-2208
LocationOrange, California
TechnologyBattery
Market / regionCAISO
Point of interconnectionMARGARITA 138 kV
Queue date2023-04-17
Proposed COD2029-05-31
IA statusNot Started