Briefing on BOBOR STORAGE

Entity Briefing
Generated Oct 6, 2026·Dataset freshness not reported
152 MW
Proposed capacity
active
Current status
Battery
Technology
CAISO
Market / region
2030-12-26
Proposed COD
C14
Queue phase
Briefing/projectactive

BOBOR STORAGE is a 152 MW Battery project in California, currently active.

The reported queue phase is C14. Proposed COD is 2030-12-26.

Queue ID
CAISO-2068
Location
Tulare, California
Technology
Battery
Market / region
CAISO
Point of interconnection
Rector Substation 230 kV

What stands out

1

BOBOR STORAGE is a 152 MW Battery project in California with status active.

2

The reported queue phase is C14; proposed COD is 2030-12-26.

Market and operating context

Queue date
2021-04-15
Proposed COD
2030-12-26
IA status
System Impact Study
Study phase
C14
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

BOBOR STORAGE — verified asset snapshot

FieldValue
Queue IDCAISO-2068
LocationTulare, California
TechnologyBattery
Market / regionCAISO
Point of interconnectionRector Substation 230 kV
Queue date2021-04-15
Proposed COD2030-12-26
IA statusSystem Impact Study