Briefing on Bluefox Solar 3

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
202 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2030-04-18
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Bluefox Solar 3 is a 202 MW Solar project in Texas, currently active.

Industrial November Project LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2030-04-18.

Queue ID
ERCOT-28INR0064
Location
Matagorda, Texas
Technology
Solar
Developer
Industrial November Project LLC
Market / region
ERCOT
Point of interconnection
#8754 Zoisite 345kV

What stands out

1

Bluefox Solar 3 is a 202 MW Solar project in Texas with status active.

2

Industrial November Project LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2030-04-18.

Market and operating context

Queue date
2024-03-22
Proposed COD
2030-04-18
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Bluefox Solar 3 — verified asset snapshot

FieldValue
Queue IDERCOT-28INR0064
LocationMatagorda, Texas
TechnologySolar
DeveloperIndustrial November Project LLC
Market / regionERCOT
Point of interconnection#8754 Zoisite 345kV
Queue date2024-03-22