Bigway Solar II is a 203 MW Solar project in Texas, currently active.
NextEra Energy Interconnection Holdings, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-12-31.
- Queue ID
- ERCOT-27INR0128
- Location
- King, Texas
- Technology
- Solar
- Developer
- NextEra Energy Interconnection Holdings, LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345KV #59904 Cottonwood - #60500 Edith Clarke Ckt #2
What stands out
1
Bigway Solar II is a 203 MW Solar project in Texas with status active.
2
NextEra Energy Interconnection Holdings, LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2027-12-31.
Market and operating context
- Queue date
- 2023-12-20
- Proposed COD
- 2027-12-31
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.