Briefing/projectactive
Big Rooter East Storage is a 201 MW Solar+Battery project in Texas, currently active.
Big Rooter East, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2029-12-31.
- Queue ID
- ERCOT-29INR0018
- Location
- Robertson, Texas
- Technology
- Solar+Battery
- Developer
- Big Rooter East, LLC
- Market / region
- ERCOT
- Point of interconnection
- 39950 TNP One Plant 345 kV
What stands out
1
Big Rooter East Storage is a 201 MW Solar+Battery project in Texas with status active.
2
Big Rooter East, LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2029-12-31.
Market and operating context
- Queue date
- 2024-03-22
- Proposed COD
- 2029-12-31
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.