Briefing/projectactive
Big Pine Solar is a 150 MW Solar project in Virginia, currently active.
The reported queue phase is IA Executed. Proposed COD is 2031-08-01.
- Queue ID
- PJM-AE2-051
- Location
- Sussex, Virginia
- Technology
- Solar
- Market / region
- PJM
- Point of interconnection
- Carson-Septa 500 kV
What stands out
1
Big Pine Solar is a 150 MW Solar project in Virginia with status active.
2
The reported queue phase is IA Executed; proposed COD is 2031-08-01.
3
Latest linked story: “Richland County boosts green energy” (WLTX, 2025-07-09).
Market and operating context
- Queue date
- 2019-02-01
- Proposed COD
- 2031-08-01
- IA status
- IA Executed
- Study phase
- IA Executed
- Service type
- NRIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.