Briefing on Benitoite Storage

Entity Briefing
Generated Oct 5, 2026·Dataset freshness not reported
126 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2027-08-25
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Benitoite Storage is a 126 MW Battery project in Texas, currently active.

BT Van Storage, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-08-25.

Queue ID
ERCOT-27INR0223
Location
Van Zandt, Texas
Technology
Battery
Developer
BT Van Storage, LLC
Market / region
ERCOT
Point of interconnection
Tap 138kV 3183 VAN_8 - 3197 TYLERSW_8

What stands out

1

Benitoite Storage is a 126 MW Battery project in Texas with status active.

2

BT Van Storage, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-08-25.

Market and operating context

Queue date
2024-03-22
Proposed COD
2027-08-25
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Benitoite Storage — verified asset snapshot

FieldValue
Queue IDERCOT-27INR0223
LocationVan Zandt, Texas
TechnologyBattery
DeveloperBT Van Storage, LLC
Market / regionERCOT
Point of interconnectionTap 138kV 3183 VAN_8 - 3197 TYLERSW_8
Queue date2024-03-22
Proposed COD2027-08-25