Query
Bee Branch IA
Type
Entity Briefing
Entity
Bee Branch IA
State
IA
Generated
2026-10-19T15:25:28.605Z

Briefing on Bee Branch IA

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
203 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2027-06-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Bee Branch IA is a 203 MW Battery project in Texas, currently active.

Tidwell Prairie LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-06-01.

Queue ID
ERCOT-23INR0421
Location
Robertson, Texas
Technology
Battery
Developer
Tidwell Prairie LLC
Market / region
ERCOT
Point of interconnection
Tap TNP ONE 39950 and Twin Oak 3400

What stands out

1

Bee Branch IA is a 203 MW Battery project in Texas with status active.

2

Tidwell Prairie LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-06-01.

Market and operating context

Queue date
2021-11-15
Proposed COD
2027-06-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Bee Branch IA — verified asset snapshot

FieldValue
Queue IDERCOT-23INR0421
LocationRobertson, Texas
TechnologyBattery
DeveloperTidwell Prairie LLC
Market / regionERCOT
Point of interconnectionTap TNP ONE 39950 and Twin Oak 3400
Queue date2021-11-15
Proposed COD2027-06-01