Briefing/projectsuspended
Bedington Energy Facility is a 100 MW Solar project in Maryland, currently suspended.
The reported queue phase is IA Executed. Proposed COD is 2025-10-31.
- Queue ID
- PJM-AE2-333
- Location
- Frederick, Maryland
- Technology
- Solar
- Market / region
- PJM
- Point of interconnection
- Bedington 138 kV
What stands out
1
Bedington Energy Facility is a 100 MW Solar project in Maryland with status suspended.
2
The reported queue phase is IA Executed; proposed COD is 2025-10-31.
Market and operating context
- Queue date
- 2019-04-01
- Proposed COD
- 2025-10-31
- IA status
- IA Executed
- Study phase
- IA Executed
- Service type
- NRIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.