Briefing on Bedington Energy Facility

Entity Briefing
Generated Oct 11, 2026·Dataset freshness not reported
100 MW
Proposed capacity
suspended
Current status
Solar
Technology
PJM
Market / region
2025-10-31
Proposed COD
IA Executed
Queue phase
Briefing/projectsuspended

Bedington Energy Facility is a 100 MW Solar project in Maryland, currently suspended.

The reported queue phase is IA Executed. Proposed COD is 2025-10-31.

Queue ID
PJM-AE2-333
Location
Frederick, Maryland
Technology
Solar
Market / region
PJM
Point of interconnection
Bedington 138 kV

What stands out

1

Bedington Energy Facility is a 100 MW Solar project in Maryland with status suspended.

2

The reported queue phase is IA Executed; proposed COD is 2025-10-31.

Market and operating context

Queue date
2019-04-01
Proposed COD
2025-10-31
IA status
IA Executed
Study phase
IA Executed
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Bedington Energy Facility — verified asset snapshot

FieldValue
Queue IDPJM-AE2-333
LocationFrederick, Maryland
TechnologySolar
Market / regionPJM
Point of interconnectionBedington 138 kV
Queue date2019-04-01
Proposed COD2025-10-31
IA statusIA Executed