Briefing/projectactive
Barkley Creek Solar is a 312 MW Solar project in Texas, currently active.
174 Power Global Properties, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-10-15.
- Queue ID
- ERCOT-28INR0324
- Location
- Lampasas, Texas
- Technology
- Solar
- Developer
- 174 Power Global Properties, LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345 kV Line from Russel Gap Switch (Bus# 3348) - Killeen Switch (Bus# 3422)
What stands out
1
Barkley Creek Solar is a 312 MW Solar project in Texas with status active.
2
174 Power Global Properties, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2029-10-15.
Market and operating context
- Queue date
- 2025-08-26
- Proposed COD
- 2029-10-15
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.