Query
BALDY MESA
Type
Entity Briefing
Entity
BALDY MESA
Generated
2026-10-12T02:17:36.553Z

Briefing on BALDY MESA

Entity Briefing
Generated Oct 12, 2026·Dataset freshness not reported
225 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
CAISO
Market / region
2026-11-01
Proposed COD
C10
Queue phase
Briefing/projectactive

BALDY MESA is a 225 MW Solar+Battery project in California, currently active.

The reported queue phase is C10. Proposed COD is 2026-11-01.

Queue ID
CAISO-1413
Location
San Bernardino, California
Technology
Solar+Battery
Market / region
CAISO
Point of interconnection
Roadway Substation 115kV bus

What stands out

1

BALDY MESA is a 225 MW Solar+Battery project in California with status active.

2

The reported queue phase is C10; proposed COD is 2026-11-01.

3

Latest linked story: “A new solar-storage project is powering Amazon data centers. It took 7 years to get online” (Latitude Media, 2024-10-28).

Market and operating context

Queue date
2017-05-01
Proposed COD
2026-11-01
IA status
IA Executed
Study phase
C10
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

BALDY MESA — verified asset snapshot

FieldValue
Queue IDCAISO-1413
LocationSan Bernardino, California
TechnologySolar+Battery
Market / regionCAISO
Point of interconnectionRoadway Substation 115kV bus
Queue date2017-05-01
Proposed COD2026-11-01
IA statusIA Executed