Briefing/projectactive
BALDY MESA is a 225 MW Solar+Battery project in California, currently active.
The reported queue phase is C10. Proposed COD is 2026-11-01.
- Queue ID
- CAISO-1413
- Location
- San Bernardino, California
- Technology
- Solar+Battery
- Market / region
- CAISO
- Point of interconnection
- Roadway Substation 115kV bus
What stands out
1
BALDY MESA is a 225 MW Solar+Battery project in California with status active.
2
The reported queue phase is C10; proposed COD is 2026-11-01.
3
Latest linked story: “A new solar-storage project is powering Amazon data centers. It took 7 years to get online” (Latitude Media, 2024-10-28).
Market and operating context
- Queue date
- 2017-05-01
- Proposed COD
- 2026-11-01
- IA status
- IA Executed
- Study phase
- C10
- Service type
- NRIS