Briefing on Azalea Wind 1

Entity Briefing
Generated Oct 10, 2026·Dataset freshness not reported
50 MW
Proposed capacity
active
Current status
Wind
Technology
NYISO
Market / region
2029-12-01
Proposed COD
C24
Queue phase
Briefing/projectactive

Azalea Wind 1 is a 50 MW Wind project in New York, currently active.

Azalea Wind LLC is the reported developer. The reported queue phase is C24. Proposed COD is 2029-12-01.

Queue ID
NYISO-C24-366
Location
Schuyler, New York
Technology
Wind
Developer
Azalea Wind LLC
Market / region
NYISO
Point of interconnection
Montour Falls to Coddington Road 115kV

What stands out

1

Azalea Wind 1 is a 50 MW Wind project in New York with status active.

2

Azalea Wind LLC is the reported developer.

3

The reported queue phase is C24; proposed COD is 2029-12-01.

4

Latest linked story: “NY Wind Farm, 19 Miles off Long Branch, Resumes Construction” (Two River Times, 2025-05-29).

Market and operating context

Queue date
2024-10-15
Proposed COD
2029-12-01
Study phase
C24

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Azalea Wind 1 — verified asset snapshot

FieldValue
Queue IDNYISO-C24-366
LocationSchuyler, New York
TechnologyWind
DeveloperAzalea Wind LLC
Market / regionNYISO
Point of interconnectionMontour Falls to Coddington Road 115kV
Queue date2024-10-15
Proposed COD2029-12-01