Briefing/projectactive
Aurelius 3 Wind is a 623 MW Wind project in Texas, currently active.
IP Roman III, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-03-31.
- Queue ID
- ERCOT-29INR0012
- Location
- Deaf Smith, Texas
- Technology
- Wind
- Developer
- IP Roman III, LLC
- Market / region
- ERCOT
- Point of interconnection
- 23908 Deaf Smith station 345kV
What stands out
1
Aurelius 3 Wind is a 623 MW Wind project in Texas with status active.
2
IP Roman III, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2029-03-31.
Market and operating context
- Queue date
- 2023-12-04
- Proposed COD
- 2029-03-31
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.