ATLAS COMPLEX is a 4.4 GW Solar+Battery project in Arizona, currently active.
The reported queue phase is C10. Proposed COD is 2027-10-31.
- Queue ID
- CAISO-1402
- Location
- La Paz, Arizona
- Technology
- Solar+Battery
- Market / region
- CAISO
- Point of interconnection
- Delaney-Colorado River 500 kV Line
What stands out
1
ATLAS COMPLEX is a 4.4 GW Solar+Battery project in Arizona with status active.
2
The reported queue phase is C10; proposed COD is 2027-10-31.
3
Latest linked story: “TransGrid Energy secures US$1.4 billion for two Arizona BESS totalling 450MW/1,800MWh” (Energy-Storage.News, 2025-02-25).
Market and operating context
- Queue date
- 2017-05-01
- Proposed COD
- 2027-10-31
- IA status
- IA Executed
- Study phase
- C10
- Service type
- NRIS
Why it matters