Briefing on Aster Solar

Entity Briefing
Generated Oct 5, 2026·Dataset freshness not reported
161 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2029-06-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Aster Solar is a 161 MW Solar project in Texas, currently active.

Aster Solar is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-06-01.

Queue ID
ERCOT-24INR0115
Location
Guadalupe, Texas
Technology
Solar
Developer
Aster Solar
Market / region
ERCOT
Point of interconnection
7042 Zorn 345kV

What stands out

1

Aster Solar is a 161 MW Solar project in Texas with status active.

2

Aster Solar is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2029-06-01.

4

Latest linked story: “Residents voice concerns over solar farm construction” (Bandera Bulletin, 2025-02-12).

Market and operating context

Queue date
2021-09-21
Proposed COD
2029-06-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Aster Solar — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0115
LocationGuadalupe, Texas
TechnologySolar
DeveloperAster Solar
Market / regionERCOT
Point of interconnection7042 Zorn 345kV
Queue date2021-09-21