1
Generators
17 MW
Capacity
N/A
Capacity Factor
0
Queue Projects

Asheville BESS, a 17 MWH battery storage plant under construction by Duke Energy Progress, represents a key investment in grid modernization but faces inherent natural catastrophe risks.

Overview

  • Project Name: Asheville BESS
  • Technology: Batteries
  • Status: Under construction
  • Parent Company: Duke Energy
  • EIA Operator: Duke Energy Progress - (NC)
  • Ownership: Duke Energy Progress - (NC)

Fleet Details

  • Capacity: 17 MWH
  • Generators: 1

Financial Profile

  • Capital Expenditure: $1361/kW (Source: eia_agg_cost)

Risk Factors and Constraints

  • Natural Catastrophe Risk: R12_NATCAT_FM (Financial modeling for natural catastrophes)
  • Operational Constraint: Experienced an ice storm warning and power outages affecting tens of thousands of customers in the Upstate region, as reported by Duke Energy and Blue Ridge Electric.

Asheville BESS represents a new battery storage asset for Duke Energy Progress, currently under construction. Its financial profile indicates a significant capital investment, and like other regional assets, it faces potential operational challenges from natural catastrophes such as ice storms.