Carolina Storage Midland is a 205 MW Battery project in Texas, currently active.
CSE Storage, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-10-03.
- Queue ID
- ERCOT-25INR0629
- Location
- Howard, Texas
- Technology
- Battery
- Developer
- CSE Storage, LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345kV 10057 Prong Moss Switch - 10062 Rockhound Switch CKT 1
What stands out
1
Carolina Storage Midland is a 205 MW Battery project in Texas with status active.
2
CSE Storage, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2028-10-03.
Market and operating context
- Queue date
- 2024-07-01
- Proposed COD
- 2028-10-03
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.