Briefing/projectactive
Aquilla Lake 3 Wind is a 297 MW Wind project in Texas, currently active.
Aquilla Lake 3 Wind is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-11-20.
- Queue ID
- ERCOT-22INR0499
- Location
- Hill, Texas
- Technology
- Wind
- Developer
- Aquilla Lake 3 Wind
- Market / region
- ERCOT
- Point of interconnection
- tap 345 kV 68040 Kopperl to 68091 Navarro
What stands out
1
Aquilla Lake 3 Wind is a 297 MW Wind project in Texas with status active.
2
Aquilla Lake 3 Wind is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2026-11-20.
Market and operating context
- Queue date
- 2021-03-08
- Proposed COD
- 2026-11-20
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.