Briefing on AP Greenport

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
100 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2027-11-19
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

AP Greenport is a 100 MW Battery project in Texas, currently active.

AP Greenport is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-11-19.

Queue ID
ERCOT-23INR0474
Location
Travis, Texas
Technology
Battery
Developer
AP Greenport
Market / region
ERCOT
Point of interconnection
Austrop – Lost Pines 345 kV transmission line (Bus #7040 – 9041)

What stands out

1

AP Greenport is a 100 MW Battery project in Texas with status active.

2

AP Greenport is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-11-19.

Market and operating context

Queue date
2022-06-10
Proposed COD
2027-11-19
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

AP Greenport — verified asset snapshot

FieldValue
Queue IDERCOT-23INR0474
LocationTravis, Texas
TechnologyBattery
DeveloperAP Greenport
Market / regionERCOT
Point of interconnectionAustrop – Lost Pines 345 kV transmission line (Bus #7040 – 9041)
Queue date2022-06-10
Proposed COD2027-11-19