Coal-fired power plants, primarily using bituminous coal (BIT) and subbituminous coal (SUB), constitute a significant portion of Indiana's operating electricity generation capacity.
Natural gas (NG) also represents a substantial component of Indiana's electricity generation capacity.
This is a focused evidence brief, not a complete decision report. It preserves the useful findings while making the decision-critical gaps explicit.
Research findings
Solar (SUN) and wind (WND) energy sources contribute meaningfully to Indiana's overall power generation capacity, though less than coal and natural gas.
Why it matters: The Mammoth Solar project is an example of solar development in Indiana.
Indiana Michigan Power (I&M) is planning for the future of the Rockport plant, aiming to transform it into a full-fledged energy hub.
Why it matters: Indiana Michigan Power, owned by Commercial Development Company, is the primary actor.
Duke Energy is actively pursuing natural gas generation projects in the U.S., with significant investment across active and proposed projects.
Why it matters: Duke Energy is a major utility and operator in Indiana.
Alcoa is evaluating a $100 million investment to restart a fourth aluminum production line at its Warrick facility in Indiana, suggesting potential increased power demand.
Why it matters: Alcoa's decision could impact the demand for power from the Warrick plant.
CenterPoint Energy is incurring significant costs to keep Unit Two of the F.B. Culley coal plant operational, despite previous plans for its closure in 2025.
Why it matters: CenterPoint Energy is the operator facing these operational challenges.
Hallador Energy is considering a 515 MW gas expansion at the Merom Power Plant, alongside reporting strong financial results for 2025.
Why it matters: Hallador Energy Company, operating the Merom plant, is pursuing this expansion.
Evidence gaps
- The available records are a bounded snapshot; a complete population was not established.
- The source did not report an authoritative data date, so current-state conclusions remain preliminary.