Briefing/projectactive
Alkali Creek Wind 2 is a 250 MW Wind project in Texas, currently active.
Alkali Creek Wind, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-12-01.
- Queue ID
- ERCOT-28INR0478
- Location
- Fisher, Texas
- Technology
- Wind
- Developer
- Alkali Creek Wind, LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345 kV BUS #1048 Tonkawa - BUS #11050 Dusty Road
What stands out
1
Alkali Creek Wind 2 is a 250 MW Wind project in Texas with status active.
2
Alkali Creek Wind, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2028-12-01.
Market and operating context
- Queue date
- 2025-12-17
- Proposed COD
- 2028-12-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.