Briefing on Alila BESS II

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
206 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2029-01-25
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Alila BESS II is a 206 MW Solar+Battery project in Texas, currently active.

Electra Energy Project, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-01-25.

Queue ID
ERCOT-29INR0207
Location
San Patricio, Texas
Technology
Solar+Battery
Developer
Electra Energy Project, LLC
Market / region
ERCOT
Point of interconnection
8249 Angstrom 345kV

What stands out

1

Alila BESS II is a 206 MW Solar+Battery project in Texas with status active.

2

Electra Energy Project, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2029-01-25.

Market and operating context

Proposed COD
2029-01-25
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Alila BESS II — verified asset snapshot

FieldValue
Queue IDERCOT-29INR0207
LocationSan Patricio, Texas
TechnologySolar+Battery
DeveloperElectra Energy Project, LLC
Market / regionERCOT
Point of interconnection8249 Angstrom 345kV
Proposed COD2029-01-25
IA statusFacility Study