Briefing/projectactive
Abilene Elmcreek BESS is a 10 MW Battery project in Texas, currently active.
DGSP2 is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-01-30.
- Queue ID
- ERCOT-25INR0701
- Location
- Taylor, Texas
- Technology
- Battery
- Developer
- DGSP2
- Market / region
- ERCOT
- Point of interconnection
- Station Name: Abilene Elm Creek TSP Station Code: ELMCRK Load Transformer name: LOAD1 Bus#: 6255 Voltage in kV (Transmission Level): 138kV
What stands out
1
Abilene Elmcreek BESS is a 10 MW Battery project in Texas with status active.
2
DGSP2 is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2026-01-30.
Market and operating context
- Queue date
- 2024-09-12
- Proposed COD
- 2026-01-30
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.